First pre-trial hearing held Monday for 530 TPC explosion-related lawsuits
First pre-trial hearing held Monday for 530 TPC explosion-related lawsuits
Court proceedings started on Monday in the first pre-trial hearing related to the TPC Group facility explosion in Port Neches.
Judge Courtney Arkeen presided over the first hearing about 10 months after the plant exploded in late November 2019.
Arkeen told 12News Monday allowed lawyers on both sides to meet and talk about logistics.
As of October 5, there are 530 individual lawsuits filed.
Judge Arkeen presides over the 128th district court in Orange County. You may be wondering why she is handling the hearings since the explosion happened in Jefferson County.
First, there are several lawsuits involved. For example, Brent Coon & Associates will represent more than 1,000 plaintiffs.
“The explosion impacted the bulk of the Mid-County region, the blast radius caused the evacuation of many thousands of people. A lot of properties were damaged,” Coon said.
Lawyer Mark Sparks is also working with a number of those affected by the explosion.
TPC’s attorneys asked the Texas Supreme Court for a request to consolidate all the claims to one district judge to ensure the cases are all handled the same.
A multi-district litigation panel ruled over the summer to allow that to happen, and Arkeen was appointed.
Arkeen told 12News she’ll handle the pre-trial matters, and then she’ll send the lawsuits back to the original courts for trial.
“So what Judge Arkeen does is she works all of the cases up for trial, so what does that mean? She handles challenges to experts, motions for summary judgement issues regarding preservation of evidence,” Sparks said.
Sparks and Coon say the process means they’ll work together to gather evidence and find out what happened on that November night nearly a year ago.
search
our offices
FROM THE BLOG
TEXAS LAWYER – Judge Spends 3 Hours Explaining His Decision
TEXAS LAWYER – January 17, 2025 – By Adolfo Pesquera A judge sympathetic to the hundreds of victims of the massive Port Neches refinery explosion was not able to convince the defendant corporation to pay $292 A proposed plea agreement between federal prosecutors and TPC Group that involved negotiations that excluded the crime victims, fell…
FEDERAL JUDGE LOWERS THE BOOM ON TPC FOR CRIMINAL CHARGES BROUGHT BY THE DEPARTMENT OF JUSTICE / TPC WALKS
FEDERAL JUDGE LOWERS THE BOOM ON TPC FOR CRIMINAL CHARGES BROUGHT BY THE DEPARTMENT OF JUSTICE / TPC WALKS On Friday, January 10, 2025, Federal Court Judge Michael Truncale called the attorneys representing the victims of the TPC refinery explosion case, TPC defense counsel and the Government prosecutors back to his courtroom so he could…
UPDATE ON TPC LITIGATION – TPC Withdraws from Plea Agreement
Beaumont — TPC has withdrawn from its plea agreement with the government during a federal sentencing hearing for the 2019 plant explosion and fire in Port Neches, based on the judge’s decision to increase restitution, and TPC is now prepared to go to trial. U.S. District Court Judge Michael Truncale held the hearing Friday at…